Preparation
Get this sorted before any timber gets cut.
Site checks
- Clear the old decking and subframe fully. Lift boards, unscrew and remove every old joist and perimeter timber. Check for any rot that's spread into the ground contact points.
- Inspect your existing support blocks. You've confirmed these are still sound and slightly raised — good, that's your levelling work basically done. Just check each one is stable and not rocking.
- Fill any gaps in the pad layout. Pick up plastic adjustable deck support pads for any spot the old blocks don't cover, aiming for roughly a 750mm grid under the frame.
- Weed membrane. If it's not already down under the old blocks, lay heavy-duty membrane across the full 3x3m area (with a bit of overlap) before the frame goes down.
- Check the fall. Confirm the pads give you a slight fall away from the house — a few mm across the 3m is plenty, just enough that water doesn't sit.
Tools you'll want on hand
- Tape measure
- Spirit level (long one, or a straight edge + short level)
- Chalk line
- Set square / speed square
- Circular saw or mitre saw
- Drill driver + bits
- Pencil / marker
- Safety glasses, gloves, ear defenders
- Clamps (handy for holding joists square while fixing)
- Wood preservative + small brush (for cut ends)
Notes
Anything you want to jot down as you go — this saves automatically.
What to Buy
Tick items off as you buy them, and fill in quantity + price paid — it's all saved on this device automatically.
| Item | Spec / needed | Qty bought | Price each (£) | Line total | Notes |
|---|
Total spent so far
£0.00
Build Order
Boards run away from the house, joists run parallel to the house wall. Fence sides: far edge and right. Open sides: near (house) edge and left edge.
- 1. Strip out. Remove all old decking boards and the old subframe completely. Dispose of rotten timber.
- 2. Ground check. Confirm existing support blocks are solid, level to a slight fall away from the house, add plastic pads to fill any gaps (~750mm grid). Lay membrane if needed.
- 3. Build the perimeter frame. 47x150mm treated timber: two 3000mm lengths and two 2906mm lengths, screwed/bracketed into a square. Check it's square by measuring both diagonals — equal diagonals means square.
- 4. Fit internal joists. 47x100mm treated timber, 9 pieces at 2906mm, running parallel to the house wall (perpendicular to where the boards will run), spaced at 300mm centres.
- 5. Fit the noggins. 47x100mm, one row at 750mm, one at 1500mm, one at 2250mm from the near edge. All noggins run parallel to each other and to the perimeter — no angles. One per bay in every row. Alternate which side you screw in from, bay to bay.
- 6. Blocking for fascia. Double up (or add a flush blocking piece) behind the two open sides — near/house edge and left edge — so there's solid timber to fix the fascia trim into later.
- 7. Level and square check. Before boards go down, re-check the whole frame is level, square, and sitting firm on every pad.
- 8. Lay the boards. Start with a full board on the open left edge (factory edge on show). Run boards away from the house, 19 boards total, ~8mm gap between each (check your manufacturer's tolerance — usually 5-10mm). Screw into every joist crossing. Last board finishes a few mm short of the fence — no cutting needed.
- 9. Fit the fascia trim. Cover the two open sides only — one trim over the board ends (near/house side), one over the long edge (left side). Fence sides need nothing.
- 10. Final check. Sweep off, check screws are all seated, check the fall still drains properly, stand back and admire it.